Tuesday, August 8, 2017

Three volunteers this morning, two after lunch, Ken, Tom and myself. The walls were re-touched/painted. Same for door and frames. Ken worked with assistants and got up 6 doors. Casing on most of those. Some base installed and caulked. Gutters were installed this afternoon.

Bedroom base can be completed in 2 rooms, 3rd needs case inside and out. All casing needs nail holes filled and caulking.

Ken will bring a table saw on Thursday to rip the needed casings. Cabinets are on site. Shelves and by-pass door tracks can be installed.

We will need at least one more gallon of trim finish paint to do touch-up throughout the house once all casing and base is installed.

Bob Gray