Monday, September 16, 2019

I was on site today. Tim and Max from Habitat were also on site. 

Tim was able to get a rock hound to help prepare the yard for sod.

This piece of equipment made a remarkable improvement. Many of the rocks are gone and the yard is much smoother.

We will still need to rake and smooth some areas and also prepare the edges next to the walks. We should be able to do this and lay the sod tomorrow (Tuesday).

The sod is expected early in the morning

Because of the high heat expected, I am suggesting an early start. I will be there by 7:30 so make your plans accordingly.

Brewer Plumbing was on site and were getting this phase completed.

Also the carpeting was being layed. Hopefully Detmer and Dillard will be there tomorrow to finish the HVAC and the electrical.

I hope to see many of you there tomorrow.

Ken 