Tuesday, June 4, 2019

We had a crew of 7 today. Tim, Ron, Ron, Norb, Steve, Dave and myself.

We arrived to a house with the roof complete. A big thank you to Enterprise for another job well done.

We accomplishes the following:

 – Finished installing the joist hangers on the ladders between the trusses above the stairs. 

 – Adjusted the front door to assure the locks will work

 – Installed insulation and thermoplye behind the shower area on the first floor

 – Installed flooring in the storage area at the top of the stairs 

 – Began the vinyl siding by installing the outside corners at the rear of the house and started installing the siding on the north side .

 – Assisted Carter Lumber in loading extra presssure treated materials.

Overall a good day.

Hopefully the weather will cooperate and we can continue with siding and building walls upstairs.

Ken