Wednesday, June 26, 2019

Six volunteers comprised of 4 regulars (Ken, Steve, Tom B., Bob) and 2 sign ups (Tom, Bill).  Ken and Tom left at noon.

Work today:

  Porch posts were reset with new specifications from Tim,

  Started south gable end siding,

  Installed south gable end window,

  Cleanup up inside for delivery of drywall and insulation,

  Drywall and insulation have been delivered and stacked on both floors based on requirements.

Tomorrow:

  Work on gable end siding,

  Start insulation.

Given the very high temperatures on the roof and not wanting to damage the shingles we called it a day at 2:30.

Bob Duplain