July 28, 2021

The project is on hold for volunteers as HVAC and Plumbing work continues. Synergy agreed to move the dirt piles around so space to build the shed could be done next week.  The big dig may also occur next week to connect the house to sewer and water.  Meanwhile, the house is full serving as a storage space and the trades are cutting holes and fitting pieces.  The materials for the shed are on site.  Siding work is on hold until drywall can be unloaded on floor 2 so the window can be installed. 

Hopefully we can get going again next week.