Saturday, August 14, 2021

Progress continues on the CtBS West Carrolton house. The electrical line has been run to the meter and was buried.  Power has not been connected as of Saturday.  The sewer, water and cable connections have been run.   Water has been connected to a meter so Tim is trying to get an outside faucet connected to have running water on site.

WP AFIT volunteers came Saturday and installed drywall in the front bedroom and the high part of the stairway.  If you work Tuesday, the cut piece in the back bedroom should be the next piece to be installed on the north side of the stairway.  We made a list of things for Carter to pick up.  More drywall this week.  Nice work on the upstairs ceilings.