Saturday, August 7, 2021

The heat and humidity didn’t keep work for continuing this week. A crew rented a lift and completed the siding and fascia after installing the last window – and yes the drywall is inside!.  The HVAC, plumbing and electric rough-ins are done and inspections are on tap for next week. Tim and others trenched for the power line, and cleanup work was completed Saturday to install the line.  Most of the surplus sand was used in the trench and some remains for covering the installed line.  The site is very clean with trash, brush and cardboard hauled away Friday and Saturday.

After inspections, it will be time to insulate and then drywall.